ISLAMABAD: The Central Power Purchasing Agency-Guaranteed (CPPA-G) has projected an approximately 8% increase in the average power purchase price (PPP) for distribution companies (Discos) to Rs27.309 per unit for calendar year 2027, compared with Rs25.320 per unit approved for 2026, raising concerns about further pressure on electricity tariffs.

The projection was presented during a public hearing held by the National Electric Power Regulatory Authority (NEPRA) on Tuesday to examine CPPA-G’s projected power purchase price report, which will serve as the basis for rebasing consumer-end electricity tariffs effective January 1, 2027.

The proposed increase reflects the continuing impact of capacity payments, fuel costs and transmission-related expenses on the power sector, despite government efforts to reduce generation costs and renegotiate agreements with independent power producers (IPPs).

CPPA-G, represented by its Chief Executive Officer Rihan Akhtar, presented six different scenarios for estimating electricity purchase costs during 2027, highlighting uncertainties surrounding international fuel prices, LNG availability, exchange-rate movements, electricity demand and hydrological conditions.

Under the base-case scenario, the agency has projected total power purchase costs of Rs3.552 trillion against estimated electricity sales of 130,081 gigawatt-hours (GWh) to Discos during 2027. This translates into an average purchase price of Rs27.309 per unit, assuming electricity demand growth of 2.6% and no load management.

The ideal-case scenario projects an average purchase price of Rs25.883 per unit, with total costs estimated at Rs3.367 trillion. However, the two worst-case scenarios indicate that the purchase price could rise to Rs28.835 and Rs29.255 per unit, respectively, reflecting higher fuel expenses, variable operation and maintenance costs and capacity payments.

The demand-sensitivity scenario estimates the average purchase price at Rs27.568 per unit, while an alternative scenario based on a different mix of imported RLNG and indigenous gas projects the rate at Rs26.441 per unit.

During the hearing, NEPRA Chairman Waseem Mukhtar sought explanations from CPPA-G regarding its assumptions about RLNG supplies, rupee-dollar parity, Brent crude prices and differences in electricity demand projections submitted by CPPA-G, the Independent System and Market Operator (ISMO) and distribution companies.

The regulator also directed CPPA-G to revise its assumed Karachi Interbank Offered Rate (KIBOR) from 11.70% to 12%, a change that could affect financing-related costs incorporated into capacity payments.

Rihan Akhtar informed the hearing that the agency had classified uncertainties into low, moderate and high categories. High-risk factors included international oil prices, LNG contract rates, spot-market prices, gas availability and furnace oil prices.

Moderate uncertainties included international coal prices, freight charges, exchange-rate movements and domestic interest rates, while lower-risk factors included electricity demand growth, local inflation, domestic coal prices and hydrological conditions affecting hydropower generation.

Under the base-case assumptions, CPPA-G has estimated an exchange rate of Rs279 per dollar, US inflation of 2.10%, KIBOR of 11.70%, SOFR of 3.98% and domestic inflation of 8.20%. The exchange-rate assumption increases to Rs290 per dollar under both worst-case scenarios, while the demand-sensitivity scenario assumes electricity demand growth of only 0.70%.

A breakdown of the base-case projection shows that capacity payments constitute the largest component of the power purchase price, estimated at Rs1.914 trillion, equivalent to Rs14.717 per unit.

Fuel costs have been projected at Rs1.319 trillion, or Rs10.141 per unit, while variable operation and maintenance expenses are estimated at Rs70.575 billion, equivalent to Rs0.543 per unit.

Transmission and market-related charges have been estimated at Rs248.3 billion, translating into Rs1.909 per unit.

Under the ideal-case scenario, fuel costs are expected to decline to Rs1.134 trillion, or Rs8.714 per unit, while capacity payments remain at Rs1.914 trillion. This brings the projected average purchase price to Rs25.883 per unit.

In worst-case scenario-I, fuel costs increase to Rs1.469 trillion and capacity payments to Rs1.962 trillion, pushing the average purchase price to Rs28.835 per unit. Under worst-case scenario-II, fuel costs rise further to Rs1.524 trillion, taking the projected purchase price to Rs29.255 per unit.

Akhtar told the hearing that international crude oil prices remained uncertain because petroleum-linked fuels, including LNG, were exposed to fluctuations in global oil markets.

He said electricity purchase price estimates had been formulated on the basis of international oil and LNG prices as well as water availability for hydropower generation.

Responding to a question, he explained that electricity demand projections for 2027 had been prepared on the assumption of zero load-shedding, although the government could introduce load management if required.

Naveed Qaiser, Chief Financial Officer of the Power Planning and Monitoring Company (PPMC), said electricity demand had been met during the previous year and that new assumptions had been incorporated into the projections for 2027. He also supported continuation of the incremental electricity package for industrial consumers.

However, industrial representatives opposed the continuation of the incremental electricity package, arguing that its benefits were limited to a small segment of industries while the resulting cross-subsidies increased the burden on other consumers.

Aamir Sheikh demanded immediate suspension of the package, maintaining that it had failed to generate a significant increase in electricity demand and had imposed additional costs on more than 90% of consumers who did not benefit from it.

He also called for prospective application of fuel charges adjustments (FCAs) beginning January 1, 2027, when the rebased electricity tariff is scheduled to take effect. He argued that industries needed advance clarity about electricity costs to plan production and exports.

Sheikh warned that the Power Division had indicated that FCAs could increase two to three times during winter, creating uncertainty for industrial consumers.

He further demanded the removal of levies on furnace oil and diesel used for power generation, maximum allocation of indigenous gas to power plants and urgent resolution of South-North electricity transmission constraints.

Questioning the increase in non-fuel expenses despite the rupee strengthening from around Rs290 to Rs279 against the dollar, he urged NEPRA to scrutinise the approximately 12% non-fuel component of electricity costs.

Another Karachi-based industrial representative, Tanveer Barry, expressed concern over the projected power purchase price scenarios ranging from Rs25.883 to Rs29.255 per unit, saying they indicated the possibility of higher electricity costs during 2027.

He questioned why capacity payments remained exceptionally high despite previous assurances that negotiations with independent power producers would substantially reduce the financial burden on the power sector.

Barry also sought details of additional power plants expected to become operational during 2027 and their likely impact on capacity payments.

He advocated greater reliance on Thar coal, nuclear power, wind energy and indigenous gas instead of expensive imported fuels, including RLNG. He also urged distribution companies to reduce administrative expenses, improve recoveries, avoid unnecessary recruitment and contain circular debt.

Rehan Javed, another industrial representative, argued that the average consumer-end electricity tariff of Rs33.38 per unit during 2026 should decline rather than increase further.

He maintained that the power purchase price alone did not reflect the actual financial burden on consumers, as distribution and other charges further increased the final electricity tariff.

Javed submitted detailed objections seeking explanations from CPPA-G, ISMO, the National Grid Company (NGC), the Petroleum Division and distribution companies regarding demand forecasts, fuel assumptions, transmission constraints, merit-order violations and capacity payments.

He particularly questioned the assumption of 200 million cubic feet per day of indigenous gas in the alternative RLNG and gas-mix scenario, asking who would bear the additional cost if the projected domestic gas supplies failed to materialise.

He also sought detailed information about South-North electricity transmission constraints, actual utilisation against projected transmission capacity of 3,200 to 4,800 megawatts and the annual financial cost of transmission bottlenecks, which he said exceeded Rs400 billion.

The industrial representative further demanded an hourly explanation of deviations from the merit order, including instances where electricity was generated using expensive fuels despite the availability of cheaper alternatives.

Industry representatives also urged NEPRA to examine overlapping functions of CPPA-G, NGC, ISMO, PPIB, WAPDA and distribution companies, proposing rationalisation of the power-sector structure, reductions in staffing and salary expenses and a comprehensive three-year cost-cutting plan.

They requested the regulator to ensure that the consumer-end electricity tariff for 2027 remained below Rs33.38 per unit, incorporate its findings on industrial objections into the final determination and direct NGC to provide detailed transmission-related data.

The representatives also demanded at least seven days’ advance notice of consumer-end tariff hearings, arguing that short notice in previous years had deprived consumers of adequate time to examine the proposed figures and prepare their objections.

Meanwhile, Arif Bilvani, another intervener, sought clarification regarding the proposed increase in electricity supply to K-Electric from the national grid.

 