ISLAMABAD: A rockslide during excavation at the Tarbela 5th Extension Hydropower Project triggered water ingress into a connecting tunnel and the under-construction powerhouse, disrupting construction activities, although all workers were evacuated safely.

According to the Water and Power Development Authority (WAPDA), the incident occurred during excavation of the second bench of the Connecting Tunnel, where a weak rock formation collapsed, allowing water from the Intake Pit to enter the tunnel and powerhouse area.

Following the incident, all workers were safely evacuated, while water accumulated at the Intake Pit was completely drained. Dewatering operations at the under-construction powerhouse have also been initiated to remove the water.

Senior WAPDA officers, the project engineer and the contractor are assessing the situation to determine the measures required to address the incident and resume construction activities.

WAPDA clarified that the incident caused no damage to the main tunnel, under-construction powerhouse, tailrace culvert or switchyard. It also confirmed that no worker was injured or killed.

The 1,530-megawatt Tarbela 5th Extension Hydropower Project comprises three generating units, each having a capacity of 510MW, and is aimed at increasing Pakistan’s hydropower generation capacity.

 